New center in Tubize: Where do we stand?

At Archives Conseil, our growth goes beyond the services we offer — it is also taking shape on the ground. We’re excited to share the latest progress on the construction of our new logistics center, designed to provide even greater performance, responsiveness, and security for your archives and equipment.

 

 

Step by Step: Construction is Moving Ahead Quickly

Week of June 9, 2025: Focus on Technical Foundations

The earthworks have begun, meaning the land has been leveled and prepared to host the upcoming infrastructure.
At the same time, our technical teams have started installing the warehouse’s electrical system. These first connections are crucial — they will power surveillance equipment, digitization tools, storage systems, and more.

Week of June 26, 2025: Roof Installation Underway

A new phase begins with the installation of the roof:

  • High-performance insulation is being added to ensure optimal preservation of documents and equipment.

  • A waterproof membrane is being applied to offer long-term protection against the elements.

  • Ventilation domes are being installed to enable natural airflow and maintain consistent air quality in the storage areas.

Why Does This Matter to You?

This new center will allow us to serve you even better:

  • Faster processing and return times for your documents

  • A strengthened infrastructure to ensure confidentiality, security, and compliance

  • New dedicated spaces for our storage, digitization, and destruction services

This project is far more than a simple construction: it marks a new chapter in Archives Conseil’s commitment to quality, safety, and environmental responsibility.